Park Head Wind Turbine Inquiry
also known as: Park Head, Park Head Inquiry, Wind Turbine Inquiry.
Park Head Wind Turbine Inquiry Main Page
CANCELLED
PUBLIC INQUIRY
PARK HEAD
In November 2010 RES
appealed against non determination. The appeal was to be heard by a
Planning Inspector at a Public Inquiry, scheduled to commence on 29
June at Embleton Hall. On the 23 May RES notified the Planning
Inspectorate that they wished to amend the scheme and requested a
postponement of the Inquiry. The planning Inspectorate did not
agree to this postponement.
On 31 May, RES withdrew the
appeal. The public inquiry, due to commence on 29 June, is
therefore cancelled.
|
Appeal:
|
Appeal by RES UK & Ireland Ltd against
the non-determination of an application for a wind farm comprising
9 turbines 127 metres in height and ancillary equipment including 1
no. 80 metre anemometry mast, access tracks, control building and
substation compound with 10 metre communications mast, crane
hardstanding, underground cables, temporary construction compound,
borrow pit and 2 no. 80 metre guyed monitoring masts for an
operational period of 25 years at Land At Rayburn Lake North
East Of Park Head Farm Netherwitton Morpeth Northumberland
|
|
Applicant:
|
RES UK & Ireland Ltd
|
|
Case Officer:
|
Frances Wilkinson
|
|
Appeal Reference
Number:
|
APP/P2935/A/10/2140441
|
|
Planning Application
Reference Number:
|
09/00154/RENEIA
|
Click here to view location plan.