Park Head Wind Turbine Inquiry

also known as: Park Head, Park Head Inquiry, Wind Turbine Inquiry.

Park Head Wind Turbine Inquiry Main Page

CANCELLED

PUBLIC INQUIRY

PARK HEAD

 

In November 2010 RES appealed against non determination. The appeal was to be heard by a Planning Inspector at a Public Inquiry, scheduled to commence on 29 June at Embleton Hall. On the 23 May RES notified the Planning Inspectorate that they wished to amend the scheme and requested a postponement of the Inquiry. The planning Inspectorate did not agree to this postponement. 

 

On 31 May, RES withdrew the appeal.  The public inquiry, due to commence on 29 June, is therefore cancelled.

 

Appeal:

Appeal by RES UK & Ireland Ltd against the non-determination of an application for a wind farm comprising 9 turbines 127 metres in height and ancillary equipment including 1 no. 80 metre anemometry mast, access tracks, control building and substation compound with 10 metre communications mast, crane hardstanding, underground cables, temporary construction compound, borrow pit and 2 no. 80 metre guyed monitoring masts for an operational period of 25 years at  Land At Rayburn Lake North East Of Park Head Farm Netherwitton Morpeth Northumberland

 

 

Applicant:

RES UK & Ireland Ltd

Case Officer:

Frances Wilkinson

Appeal Reference Number:

APP/P2935/A/10/2140441

Planning Application Reference Number:

09/00154/RENEIA

 

Click here to view location plan.

 

 

 

Last updated: 01/06/11